contestada

one bricklayer can build a wall in 6 hours. another bricklayer could build the same wall in 4 hours. if they work together, how long will it take to build the wall?

Respuesta :

caylus
caylus caylus
  • 04-08-2016
Hello,

Let's
V1 the velocity of the 1st bricklayer,
V2 the velocity of the 2nd bricklayer,

1wall=V1*6==>V1=w/6
1wall=V2*4==>V2=w/4
==>V1+V2=w/6+w/4=10w*24=5w/12

Let's t the time for the 2 bricklayer to build the wall
(V1+V2)t=w
==>5w/12*t=w
==>t=12/5 (h)=2h24min.



Answer Link

Otras preguntas

There are 50 identical apples that need to be distributed among alice, bob, and cathy. determine the numberof ways that this can be done such that each one of t
why do you think spain came to believe that keeping florida was impossible?
Write true or false. The figure has rotational symmetry
In pea plants, the allele for yellow seeds is dominant to the allele for green seeds. Predict the genotypic ratio of offspring produced by crossing two parents
Under _____ uncertainty avoidance employees are willing to change jobs more frequently
Which of the following organic molecules may have up to four levels of structure? A. Proteins B. Lipids C. Nucleic Acids D. Carbohydrates
Where is freshwater drinking found in the great plains?
Which antiquated term was used during the cold war to describe communist countries that disregarded the free market in favor of planned economies? a. global nor
5 What has turned Anne’s whole world upside down in her July 8, 1942 report?
What is 3 2/3 multiplied by 4 1/2