Consider the following project network and activity times (in weeks): Activity A B C D E F G H Time 5 3 7 6 7 3 10 8 How much time will be needed to complete this project

Respuesta :

codiepienagoya codiepienagoya
  • 04-07-2021

Answer:

Please find the attached file of the complete question:

Explanation:

Please find the attached file of the solution:

Critical Path:  ACH

Duration: 21

Because C is on the Critical Path, it cannot be postponed without causing the project to be delayed.

E is not on the critical path, thus it may also be delayed by two weeks without causing the project to be delayed.

[tex]D : ES : 6, EF : 10, LS : 7, LF : 11[/tex]

Ver imagen codiepienagoya
Ver imagen codiepienagoya
Answer Link

Otras preguntas

Why do whole numbers raised to an exponent get greater wealth fractions raised to an exponent get smaller
how can a country's stock exchange help people to save and invest in money
Who was the communist leader of Cuba during the Cuban Missile Crisis? A. Joseph Stalin B. Vladimir Lenin C. Fidel Castro D. Leon Trotsky
How big is the human stomach?
25 pound x 41.000 pounds
is 7,116 divisible by 8
Many of the original English colonists were religious separatists from the church of England. Why were these groups eager to settle colonies in North America?
find the distance between points P(1,2) and Q(4,8) to the nearest tenth
what 2 states border new york
You're attempting to determine the amount of usable floor space in your day care facility. Which one of the following areas can you include in your calculation?