pieman33333 pieman33333
  • 04-04-2018
  • Mathematics
contestada

Three workers can do a job in 28 hours. How many more workers are needed to do this job in 12 hours?

Respuesta :

MrRamon
MrRamon MrRamon
  • 13-04-2018
4 additional workers for 7 total workers.
if it takes 3 workers 28 hours to do work there are 84 total hours of work (3*28=84) to find how many workers it will take to get the work done in 12 hours divide 84 by 12. 84/12= 7 total workers. 7-3= 4 additional workers needed.
Answer Link
pranilraichura
pranilraichura pranilraichura
  • 08-03-2020

Answer:

4 workers

Step-by-step explanation:

Answer Link

Otras preguntas

A. 71 B. 84 C. 29 D. 67
Write an equation for the line tangent to the graph of f at = 1/2
Find the surface area of the composite solid 6 ft 4 ft 5 ft 5 ft​
More Punnett Squares.
-7r^2= -329 square root property​
The perimeter of the square at the right is 48 inches. What is the area of the square at the right? Explain how you found your answer.
Is (8, 3) a solution to the system? - 2 + 4y = 4 - 2 + 3y = 1
What is the density of krypton gas (MM = 83.8 g/mol) at 3.00 atm and 100. °C? g/L
46. Find the length of the hypotenuse, c in this triangle.
A regular octagon with side length a cm can be made by cutting off the four corners of a square board. How long should the sides of the board be?